Bharat Heavy Electricals Ltd (BHEL) has ordered stoppage of work at the 2x800 MW Damodaram Sanjeevaiah Thermal Power Station in Krishnapatnam, Andhra Pradesh.
The move comes in the wake of the company being reportedly singled out for project delays and levied a fine of ₹240 crore for liquidated damages (LD), which Andhra Pradesh Power Development Corporation Ltd (APPDCL) has deducted.
According to sources, BHEL pointed out that though APPDCL was aware of the shortcomings of the other contractors on site, the LD was deducted unilaterally, without assessing reasons for the delay.
APPDCL’s move is against the terms and conditions and the spirit of the contract.
Comments
Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.
We have migrated to a new commenting platform. If you are already a registered user of TheHindu Businessline and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.