NMDC has signed a contract for Raw Material Handling System Package for the upcoming 3 MTPA Integrated Steel Plant at Nagarnar, with BHEL on Saturday.
Mr. G. Viswakarma, ED (Steel Plant) on behalf of NMDC and Mr. U.N. Singh GM, for BHEL signed Contract Agreement in presence of Mr Rana Som, CMD, NMDC and Mr B.P.Rao, CMD, BHEL and other dignitaries.
Mr. Rana Som said the proposed 3 MTPA steel plant would be the fastest moving steel plant project among all green field or brown field projects in the country.
Mr. B.P.Rao, CMD, BHEL said that BHEL’s group at Bangalore was fully geared up to complete this challenging job well within the stipulated time of 30 months.
The Raw Material Handling System will be handling @ 10 MT/year of raw material catering to the different units of the NMDC Steel Plant.