State-run power equipment maker BHEL on Wednesday said it has bagged an order worth ₹350 crore for setting up two 765 kV substations in West Bengal, claiming the order to be the largest for the company so far.
The order has been placed on BHEL by Powergrid Medinipur-Jeerat Transmission Ltd (PMJTL), a wholly-owned subsidiary of Power Grid Corp. The project has to be completed on Engineering, Procurement and Construction (EPC) basis.
BHEL’s scope of work in the contract envisages constructing two large-sized greenfield 3,000 MVA, 765/400 kV substations, at Medinipur and Jeerat (near Kolkata).
These Electrical High Voltage (EHV) substations will play a key role in strengthening the 765 kV system in the Eastern region for delivering power to important load centres in West Bengal.
The substations are slated to be commissioned within 30 months. The project shall be engineered and delivered by BHEL on total turnkey basis.
BHEL has been contributing significantly in making the 765 kV Ultra High Capacity inter-State transmission network a reality by undertaking the commissioning of 765 kV greenfield substations across the nation on turnkey basis.
These include substations at Raichur (3,000 MVA) in Karnataka, Fatehabad in Uttar Pradesh (3,000 MVA), Banaskantha (3,000 MVA) and Bhuj (4,000 MVA) in Gujarat and Ariyalur in Tamil Nadu (3,000 MVA).