Essar Energy said the second unit of the 2 X 600 MW Salaya I power plant in Gujarat has begun commercial operations.
The first unit commenced operations in April this year.
Most of the power produced will be sold to the Gujarat state electricity utility, GUVNL, under a long-term contract.
Essar said two more projects, the 1,200-MW Mahan I and 510-MW Vadinar P2 projects, were also scheduled for commissioning this year.
Comments
Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.
We have migrated to a new commenting platform. If you are already a registered user of TheHindu Businessline and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.