Reliance Power said that boiler light up has been achieved for its sixth 660 MW unit of the 3,960-MW Sasan ultra mega power plant in Madhya Pradesh.
Boiler light up is a critical milestone in the commissioning activity of a power plant.
RPower said 3,300 MW (five 660 MW units) of the project are already operational.
Comments
Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.
We have migrated to a new commenting platform. If you are already a registered user of TheHindu Businessline and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.