RPower's 6th Sasan unit on track for commissioning

Our Bureau Updated - March 12, 2018 at 06:55 PM.

Reliance Power said that boiler light up has been achieved for its sixth 660 MW unit of the 3,960-MW Sasan ultra mega power plant in Madhya Pradesh.

Boiler light up is a critical milestone in the commissioning activity of a power plant.

RPower said 3,300 MW (five 660 MW units) of the project are already operational.