The Central transmission utility PowerGrid Corporation has hooked up Tata Power’s 4,000—MW ultra—mega power project (UMPP) at Mundra to the national grid and the first unit of the Rs 20,000 crore plant is likely to commence electricity supply within the next four months.
“The 4,000—MW Mundra project is progressing as per schedule, with engineering, procurement and construction activities in full swing. The transmission evacuation system from PGCIL got commissioned on September 29, 2011, and the transmission capacity is currently under testing by PGCIL,” Tata Power said in an e—mailed statement.
The Tata Group firm said as per the terms of the UMPP contracts, seven months’ time is provided for stabilisation of electricity supply from a unit to the grid. However, the company aims to commence evacuation of power from the project within the next four months.
“Contractually, it requires seven months post—availability of transmission lines to stabilise a unit. We aim to stabilise Unit—1 of the Mundra UMPP in four months,” the statement added.
PGCIL confirmed that it had established the transmission network for the Mundra network and that it is ready for evacuation of power.
“From our side, the transmission network is ready and evacuation of power can start now,” a PGCIL official said.
Comments
Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.
We have migrated to a new commenting platform. If you are already a registered user of TheHindu Businessline and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.