Union Power Minister RK Singh on Tuesday said that “after some time” the government will bring in tariff barriers to protect domestic battery manufacturers. He was speaking at a web-conference organised by TERI, the Delhi-based energy and sustainability policy research organisation.
Outlining the various steps the government has been taking to foster renewable energy in India, the Minister said that there would be more auctions of wind and solar capacities combined with storage. By so scaling up, the government would bring down the cost of storage, he said.
“Right now we are inviting people to manufacture batteries in India; but after some time, we will set up tariff barriers” so that the manufacturers are not hit by cheap imports, he added.
Singh also said that the government is bringing in customs duty on imported solar cells and modules, because “our neighbour up north” is dumping the products in India, often selling below manufacturing costs. Earlier, India had faced a similar situation in ‘iron and steel’, he said.
Speaking of the huge solar capacity being rolled out, he said: “We will insist on most of it (equipment) being made here.” Already, the domestic modules and cells manufacturing capacity (cells are assembled into modules) is being expanded by 7,000-8,000 MW, he added.
Earlier, Singh pointed out that India had installed wind and solar capacity of 88 GW. “Another 145 GW is under installation, and we have bid out another 31GW,” he said.
43 GW of solar bid out in 2019-20
A research note issued by JMK Research, a Delhi-based renewable energy and e-mobility consultancy, said that 43 GW of solar capacity had been tendered out in 2019-20, compared with the country’s current installed base of 35 GW.
Of the capacity tendered out, auctions were completed for 38 GW, of which 26 GW of capacity were allocated to winning bidders.
Sources in another consultancy, MEC+, have given Business Line more or less similar estimates — 41 GW bid out, 37 GW finalized and 20 GW allocated.
It is quite another matter how much of the capacity will be actually set up, given the delays expected due to Covid-19.
“Considering the current scenario, half of the allocated 20 GW is likely to be delayed due to very competitive tariffs, issues with the grid and financial stress in banks,” Sidharth Jain, Director, MEC+ said, noting further that 5 GW of that could be cancelled.
Comments
Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.
We have migrated to a new commenting platform. If you are already a registered user of TheHindu Businessline and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.