Hyderabad Metro Rail Ltd has put on fast track work on certain stretches in order to make up for the six-month delay the project faced earlier.
Works at Uppal and Miyapur depots and foundation works on Nagole-Mettuguda stretch are being speeded up, a company release said.
The casting yard at Uppal is almost ready and casting of segments has commenced. Pillar foundation works between Nagole and Mettuguda are being taken up in a big way by the construction wing of L&T.
“Our aim is to complete as many foundations as possible out of the 305 foundations of stage-I Nagole-Mettuguda stretch before monsoon,” Mr N. V. S. Reddy, Managing Director, said.
Comments
Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.
We have migrated to a new commenting platform. If you are already a registered user of TheHindu Businessline and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.