With two months to go for 4,000 megawatt of gas-based power projects to be commissioned and fuel supplies yet to be tied up, the producers have approached the Ministry of Petroleum & Natural Gas for gas allocations.
The companies whose projects fall in this category include Reliance Power, Lanco, GVK, and GMR.
In a letter to the Petroleum Minister, Mr S. Jaipal Reddy, the Association of Power Producers, has said about 8,200 MW of gas-based generation capacity can be commissioned in the next 18 months.
Of this, about 4,000 MW of power projects are ready to commence generation well before March 31, and are awaiting gas allocation from the Empowered Group of Ministers.
Non-core sectors
The Association has suggested that the Petroleum Ministry could consider discontinuing gas allocation to non-core sectors and use the same for core sectors, namely, power and fertiliser. Currently, over 18 mscmd of gas sold under the administered price regime is being supplied to the non-priority sector.
The total gas-based power plants' capacity in the country is about 16,600 MW. These consume about 66 mscmd of gas and the average capacity utilisation for all these plants is around 70 per cent. If the capacity utilisation for all these power plants is rationalised at 60 per cent or so, about 8-10 mscmd of gas will get released which can be allocated to the upcoming 11{+t}{+h} or 12{+t}{+h} Plan power projects, it suggested.
The power sector is going through a critical phase and unless urgent policy interventions are made it will result in idling of capacity. Availability of gas is also becoming scarce due to the steep and continuous reduction in gas production from Reliance Industries-operated D6 fields. Most of the States are rationing power to both domestic and industrial consumers.
Coal-based projects
The domestic power supply situation has deteriorated significantly and nearly 51 per cent of the coal-based projects are operating with less than seven days' stocks. The demand and supply gap is increasing progressively and if we allow the existing capacity to idle it will jeopardise 12th Plan capacity addition programme, the producers said.
Public money in the form of debt provided by various Indian banks and financial institutions is at risk unless these projects start commercial operation by March 31 and start servicing debt, they said.
Comments
Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.
We have migrated to a new commenting platform. If you are already a registered user of TheHindu Businessline and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.