The power sector would require a whopping investment of about Rs 11 lakh crore in the next five years to achieve the targeted capacity addition of over 1,00,000 MW, the Economic Survey 2011—12 said.
“In order to achieve the projected capacity addition of 1,03,300 MW and build commensurate transmission and distribution capacity, investment to the tune of Rs 11.18 lakh crore would be needed,” the survey, which was tabled in Parliament on Thursday, said.
Meanwhile, the sector is likely to be constrained by shortage of fuel and environmental issues, it said.
Shortage in supply of coal and gas to the power sector has been impacting the output at present. A delay in forest and environmental clearances, in particular for hydro based power projects, has slowed down capacity addition.
A power generation capacity of 50,000 MW to 52,000 MW is expected to be added during the current Plan period ending March 31, 2012. A capacity addition of 46,669.7 MW has so far been achieved until January 2012.
At the start of the 11th Five Year Plan (2007—12), a capacity addition of 78,700 MW was envisaged but was scaled down to 62,374 MW in the mid term appraisal, with the thermal, hydro and nuclear segments contributing 50,757 MW, 8,237 MW and 3,380 MW respectively.
The country’s total power generation capacity stands at over 1,80,000 MW.
Comments
Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.
We have migrated to a new commenting platform. If you are already a registered user of TheHindu Businessline and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.