Dilip Buildcon on Tuesday said it has completed the rehabilitation and upgradation of district roads between Mandla-Pindrai and Salimnabad-Vilayatkalan in Madhya Pradesh. The project included intermediate laning or two-laning of the district roads on engineering, procurement, construction (EPC) basis. The project was completed 185 days prior to schedule, because of which the company is entitled to a bonus of ₹5.72 crore, or 3 per cent of the project cost of ₹191 crore, it said in an exchange filing. Shares of Dilip Buildcon gained 2.47 per cent at ₹306.65 on the NSE.
Comments
Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.
We have migrated to a new commenting platform. If you are already a registered user of TheHindu Businessline and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.