Dilip Buildcon on Tuesday informed the exchanges that in lieu of early completion (188 days prior) of the project in Uttar Pradesh, the company is entitled to receive a maximum bonus of ₹37.90 crore. The company had received the order for four-laning of the Lucknow-Sultanpur section under NHDP Phase-IV on hybrid annuity basis. The company received completion certificate from the authority on July 6 and has declared the project fit for entry into operation as on July 3. Shares of Dilip Buildcon closed 0.42 per cent lower at ₹427.95 on the BSE.
Comments
Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.
We have migrated to a new commenting platform. If you are already a registered user of TheHindu Businessline and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.