Land acquisition rates for Kochi Metro approved

Our Bureau Updated - October 17, 2012 at 10:30 PM.

The State Empowered Committee has approved the rates finalised by the district-level purchase committee for land acquisition in Kochi as part of the Metro Rail project.

According to the approved rates, land acquired for widening of main roads such as Banerjee Road, MG Road and South Railway Station Road will get compensation at the rate of Rs 52 lakh a cent . The rate was finalised after many rounds of discussions by the District Collector with landowners.

With the rate being approved, the district administration can go ahead with acquisition after paying 80 per cent of the due amount. Almost all the landowners along these roads agreed to hand over land at this rate, said an official press release.

Other rates

The empowered committee also approved the rate of Rs 24 lakh for a cent for acquiring land for foot overbridge near the KSRTC bus stand and also the rate of Rs 18.50 lakh a cent for acquiring land for approach road to Ponnurunni railway overbridge.

The high-level committee headed by the Chief Secretary also approved the decision to acquire land for four other development projects.

The committee approved decision to acquire 8.51 acre out of total 20 acre required for widening of Thammanam-Pullepady Road, 86 cents for Korankadavu Bridge, 2.6505 hectare for bridges across Periyar along the Airport-Seaport Road, and 51 cents for Mattathamkadavu bridge connecting Amballur and Udayamperoor.