India has spent less than a quarter of the funds available for a programme to clean up the Ganges river over the last two years, a federal audit has found, citing lapses in planning and financial management of a flagship scheme.
The government had only used $260 million of the $1.05 billion earmarked for the National Mission for Clean Ganga (NMCG) programme between April 2015 and March 2017, according to the report from the Comptroller and Auditor General of India. The water quality in eight of 10 towns surveyed along the Ganges did not meet outdoor bathing standards.
“The performance audit revealed deficiencies in financial management, planning, implementation and monitoring, which led to delays in achievement of milestones,” the auditor said in its 160-page report which was presented to parliament last week.
The Water Resources Ministry, which runs the NMCG, did not respond to a request for comment.
Prime Minister Narendra Modi’s administration committed $3 billion in 2015 for a five-year project to clean the 2,525-km (1,570-mile) river that remains heavily polluted despite being a water source for 400 million people.
Modi, who represents the holy city of Varanasi on the banks of the Ganges, had made a clean-up of the Ganges one of his key campaign promises in the 2014 presidential election.
The Ganges is arguably one of the most revered rivers in the world, and one of the most polluted. It is worshipped by Hindus, who make up about 80 per cent of India’s 1.3 billion people.
But the river, which stretches from the Himalayas to the Bay of Bengal, is also a destination for waste produced by hundreds of factories — over three-quarters of the sewage generated in the towns and cities of the crowded northern plains flows untreated into the Ganges.
When a Reuters reporter visited northern Kanpur city in March, the river in most parts of the town appeared black in colour, with its many factories and tanneries dumping waste into the Ganges. The federal auditor’s report contained pictures of untreated sewage being discharged directly into the river in several States.
Sewage treatment plants
The NMCG had set a target to award contracts for all sewage treatment plants by last year, but even by August this year it hadn’t approved projects to treat nearly 1,400 million litres of sewage daily, the report said.
“Without stopping sewage going into the river, we cannot imagine a clean Ganga. That should be the top priority,” said Rakesh Jaiswal, head of a Ganges-focussed environmental group in Kanpur since 1993.
“(The report) is a sad commentary on the government’s efforts to clean the river.”
Missed target
The NMCG told the auditor the sewage treatment problem would be resolved to an extent once projects under construction are completed, but it remained “silent” about its failure to meet its targets, the auditor’s report said.
Modi has been concerned about the slow pace of the Ganges clean-up drive and his personal secretary had demanded regular updates from project officials to track its progress, Reuters reported in April.
Modi’s office didn’t respond to a request for comment.
India had set a 2018 deadline to clean the river, but local media in October quoted the government’s new Water Resources Minister as saying that the Ganges’ water quality will likely only improve by March 2019.
Environmentalists doubted that.
“Meeting the (2019) target seems to be very difficult,” said Sushmita Sengupta of the New Delhi-based Centre for Science and Environment. “Nothing has been done in a constructive way on the ground.”
Comments
Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.
We have migrated to a new commenting platform. If you are already a registered user of TheHindu Businessline and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.