The road transport and highways sector has the maximum number of delayed projects at 300, followed by railways at 119, and petroleum sector at 90, showed a government report.
In the road transport and highways sector, 300 out of 825 projects are delayed. In railways, out of 173 projects, 119 are delayed, while for petroleum, 90 out of 142 projects are delayed, as per the latest flash report on infrastructure projects for June 2022.
The Infrastructure and Project Monitoring Division (IPMD) is mandated to monitor central sector infrastructure projects costing ₹150 crore and above based on the information provided on the Online Computerised Monitoring System (OCMS) by the project implementing agencies.
IPMD comes under the Ministry of Statistics and Programme Implementation.
Most delayed projects
The report showed that a 500 MW Prototype Fast Breeder Reactor being constructed by Bharatiya Nabhikiya Vidyut Nigam Ltd (BHAVINI) is the most delayed project. It is delayed by 168 months.
The second most delayed project is PARBATI-II hydro electric project (4X200 MW) of the NHPC, which is delayed by 162 months.
The third most delayed project is Subansiri Lower hydro electric project (8X250 MW) of NHPC at 155 months.
Road transport and highway sector
The total original cost of implementation of 825 projects when sanctioned was ₹4,90,792.42 crore. This was subsequently anticipated at ₹5,37,163.29 crore, implying a cost overrun of 9.4 per cent.
The expenditure incurred on these projects till June 2022 was ₹3,21,084.28 crore, which is 59.8 per cent of their anticipated cost.
ALSO READ: Bharatmala Project cost doubles; only 23% project completed: Report
Railway sector
The total original cost of implementation of 173 projects when sanctioned was ₹3,72,761.45 crore, which later increased to ₹6,12,578.9 crore, implying a cost overrun of 64.3 per cent.
The expenditure incurred on these projects till June 2022 was ₹3,29,682.13 crore, or 53.8 per cent of the anticipated cost.
ALSO READ: 640 infra projects running behind schedule, some up to 26 years
Petroleum sector
The total original cost of implementation of 142 projects was ₹3,73,333.65 crore, which rose to ₹3,93,008.38 crore, showing a cost overrun of 5.3 per cent.
The expenditure incurred on these projects till June 2022 was ₹1,33,493.59 crore, which is 34 per cent of the their anticipated cost.
Comments
Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.
We have migrated to a new commenting platform. If you are already a registered user of TheHindu Businessline and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.